News

A total of 28 such bridges have been planned on the entire Mumbai-Ahmedabad high-speed rail corridor, with 17 in Gujarat.
Ahmedabad-Mumbai bullet train: In a major development in the India’s first bullet train project between Ahmedabad and Mumbai ...
The Mumbai-Ahmedabad Bullet Train project has achieved a significant milestone in Gujarat with the completion of its eighth ...
The first rail level slab casting was completed at the bullet train station at Boisar in Palghar of Maharashtra ...
Mumbai: The construction of the Boisar Bullet Train station has reached a significant milestone with the successful casting ...
India's ambitious bullet train project connecting Ahmedabad and Mumbai progresses with a significant boost. A Siemens-led ...
The National High Speed Rail Corporation Limited awarded a contract to a Siemens-led consortium for the Mumbai-Ahmedabad ...
Mumbai: A 100-meter long steel bridge was successfully launched over the Dedicated Freight Corridor (DFC) tracks near Bharuch, Gujarat under Mumbai-Ahmedabad bullet train project. This bridge marks ...
Fabricated in Tiruchirappalli, the bridge was transported using custom-designed trailers. It was launched using an 84m long ...
The under-construction Vapi Bullet Train station, a key node on the Mumbai-Ahmedabad High-Speed Rail corridor, is fast taking shape at Dungra village along the Vapi-Silvassa road. The under ...
NHSRCL said, "Out of 300 km of superstructure, 257.4 km is constructed through Full Span Launching Method (FSLM) including 14 river bridges, 37.8 km through Span by Span (SBS), 0.9 km steel bridges ...
The National High Speed Rail Corporation Limited has awarded a contract to a consortium led by Dineshchandra R Agrawal (DRA) Infracon Private Limited, Siemens Limited and Siemens Mobility GmbH to ...