Indira Gandhi International Airport is set to complete major projects including the restoration of Terminal 1 by March 15, ...
The Delhi airport’s Terminal 2 (T2) will be shut for four to five months starting April for refurbishment works, after ...
Terminal 2's current passenger load, which stands at 15 million, will be shifted to Terminal 1, according to airport operator ...
Delhi's IGI Airport Terminal 2 (T2) will be closed for four to five months starting April for upgrades. One runway will also ...
According to Delhi International Airport Limited (DIAL), the closure will take place only after Terminal 1 (T1) becomes fully ...
According to DIAL CEO Videh Kumar Jaipuriar, ongoing work at Terminal 1 (T1) is expected to be completed by March 15, after ...
DIAL CEO Videh Kumar Jaipuriar said the works at T1 is expected to be completed by March 15 and will be open for flights ...
Delhi International Airport Limited (DIAL), which operates India's largest airport, dismissed the expert committee report as ...
Delhi airport operator DIAL on Wednesday said Terminal 2 (T2) is expected to be shut down for four to five months, starting ...
From terminal upgrades to critical runway enhancement, these developments aim to boost capacity and improve efficiency.